Terra Nova Additional Living Quarters

Project Description

  • Fabricated, assembled and outfitted a 600 tonne, 40 bed additional offshore accommodation module and a 100 tonne Starboard Lifeboat Enclosure (SLE) for the Terra Nova FPSO vessel

Client: Petro Canada
Duration: January 2006-June 2006
Person Hours: 250,000

« Back to Oil and Gas Projects List

Project Scope

Fabrication